Question
Which is a proper grounding method for a tower?
Answer Options
- A) A single four-foot ground rod, driven into the ground no more than 12 inches from the base
- B) A ferrite-core RF choke connected between the tower and ground
- C) A connection between the tower base and a cold water pipe
- D) Separate eight-foot ground rods for each tower leg, bonded to the tower and each other
Correct Answer: D
Explanation
No explanation yet. Help improve this by contributing below!
This topic was automatically created to facilitate community discussion about this exam question. Feel free to share study tips, memory tricks, or additional explanations!